Question 1
If 30 men working 9 hours per day can reap a field in 16 days, in how many days will 36 men reap the field working 8 hours per day?
PPSC - Junior Clerk (43J2022) - Board of Revenue - 2023
Question 2
Four men working together can dig a ditch in 42 days. If one man works only half-days, how long will it take to complete the job:
PPSC - Assistant - Clubbed Cases Various Departments - 2024