Civil Engineering Mcqs — Test 61
Page 1 of 3
Question 1
Assertion A : English method of tunneling requires more time as compared to other methods of tunneling. Reason R : In English method of tunneling, the masons and excavators have to work alternately/
Question 2
The needle beam method of tunneling______________?
Question 3
American method of tunneling________________?
Question 4
Assertion A : When rock conditions are favorable, it will not be necessary to take up concrete lining concurrently with the driving operations till the full length of the tunnel has been driven through rock. Reason R : A tunnel through rock, hard or soft, does not need any concrete lining________________?
Question 5
In the construction of Metro Railways, “Cut and Cover” method of construction is suitable in situations listed at________________?
Question 6
In “full face” method of constructing tunnels, the first operation relates to______________?
Question 7
Number of unknown internal forces in each member of a rigid jointed plane frame is_____________?
Question 8
Degree of kinematic indeterminacy of a pin-jointed plane frame is given by______________?
Question 9
If in a pin-jointed plane frame (m + r) > 2j, then the frame is________________?
Question 10
A rigid-jointed plane frame is stable and statically determinate if_______________?