Q
What characteristic best describes the cost baseline?
-
A
A. Total budget for the project
-
B
B. Time phased budget for the project
-
C
C. Total budget for the project including the contingency budget
-
D
D. Total budget for the project including the contingency budget and the management reserve
Correct Answer:
B. B. Time phased budget for the project